Phase 2 involves construction of all athletic fields, restrooms, concessions, landscaping, trails, disc golf course, tennis courts, etc. 

Update: 12.12.17: The contract for construction of the restooms, concession and maintenance buildings was awarded to Wright Builders or Temple at the 12.17.17 City Council Meeting. At the same meeting, construction of all fields, design and construction of irrigation systems, and planting of grass, tress and other plants was awarded to Sports Field Solutions. Parking, flat work and the disc golf course will be awarded at a Februaray 2018 Council meeting. 

Update: 10.05.17: Ballfield and Tennis COurt lighting was awarded to Musco Lighting at the 10.5.17 City Council Meeting. 